'Sibbi-Harnai railway track to be completed by January 2023'.

ISLAMABAD -- Pakistan Railways is likely to complete reconstruction and rehabilitation work on the strategic Sibbi-Harnai railway track by end of January 2023 with the assistance of the National Logistics Cell (NLC).

'The railway track was made dysfunctional after a series of bomb blasts that damaged as many as 22 steel bridges in the highly rugged and inaccessible area,' sources in the Ministry of Railways told reporter.

The track was badly damaged in 2006 and so far about 95 percent of the reconstruction work of the project was completed and remaining would be completed soon.

Minister for Railways Khawaja Saad Rafique had also taken keen interest in the projects and directed concerned official to complete the project at the earliest.

10 railway stations were rendered dysfunctional for lack of proper maintenance over a long period of time.

In March 2016, a contract of the rehabilitation and restoration of Sibbi-Harnai railway track along with the up-gradation of railway stations was awarded to the NLC as no other construction firm agreed to undertake the project due to prevalent security situation.

During the initial survey of the track...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT