Nikola Corporation Reports 1st Quarter 2021 Results.

PHOENIX: Nikola Corporation (Nasdaq: NKLA), a global leader in zero-emissions transportation solutions, today reported financial results for the quarter ended March 31, 2021.

"During the first quarter Nikola continued to deliver on our previously communicated milestones and execute on our business plan," said Mark Russell, Nikola's Chief Executive Officer. "We have had continued success in commissioning and validating the Nikola Tre BEVs, and are nearing completion of both our Ulm, Germany and Coolidge, Arizona manufacturing facilities."

Progress on the Commissioning and Validation of the First Batch of Nikola Tre BEVs

Commissioning and validation activities continue on the Nikola Tre battery-electric vehicle (BEV). As expected in a new program development cycle, we have had to overcome some component level delays which we have worked through with our suppliers to minimize the impact on the scheduled timeline. Q1 activities included commissioning the first batch of five Tre BEVs and validation testing at the proving grounds. As of today, powertrain performance and durability testing have started at the proving grounds.

We are nearing completion of the second batch of nine beta Nikola Tre BEVs in Ulm, Germany. As of today, we have completed eight of the nine trucks, with the ninth scheduled to be completed by May 10. Three trucks from the second batch of nine are at Nikola's headquarters (HQ) in Arizona, one is in Indiana for crash testing, and four are in transit to the HQ in Arizona. We anticipate that the four trucks in transit, in addition to the ninth truck being completed, will arrive at our HQ by the end of May.

Progress Made at our Joint Venture Manufacturing Facility on IVECO's Industrial Complex in Ulm, Germany

As of May 7, Nikola and IVECO have nearly completed the building modifications of the joint venture manufacturing facility. The dismantling and building restructuring have been completed. The automatic guided vehicle (AGV) system installation is ongoing and is expected to be completed over the next few weeks. The tool and equipment installation of the 14 separate workstations should be completed by the end of the month. Nikola is on track to begin the start of trial production in June 2021.

Progress Made at Nikola's Coolidge, Arizona Manufacturing Facility

During the first quarter of 2021, Nikola continued to make progress at the greenfield manufacturing facility in Coolidge, Arizona. The building has been substantially...