CDA approves Rs 110.119 mlns for installation, provision of gas network in sector I-11/1 and 2.

ISLAMABAD -- Capital Development Authority (CDA) in line with its policy to complete the development works in the stalled sectors, has approved Rs 110.119 millions for installation and provision of gas network in sector I-11/1 and 2.

The payment would likely be made to SNGPL in next few days and after that SNGPL will start work on the provision of Sui-gas in the sector I-11.Under this project, SNGPL would lay main gas pipe line up to the sector and will further establish door to door gas network in sector I-11/1 and 2.

The said work would likely to be completed in approximately three (03) months.

CDA-DWP in its 45th meeting held in October this year, approved PC-I and PC-IV amounting to Rs.2618.251 millions for carrying out development works in sector I-11. Consequent upon approval of Project Costs, concerned formations were directed to fulfill codel formalities so that works pertaining to respective formations be carried out simultaneously.

In this context, SNGPL was approached to furnish demand notice for provision of Sui-gas infrastructure in the sector. After complete survey demand draft was furnished which was processed and accordingly approved by the authority during the last week.

In addition to provision of Sui-gas network, authority during its board meeting held in November this year approved the allocation of 18.6 kanals land for construction of 132 KV grid station in sector I-11/2 for provision of electricity in the sector I-11 and I-12. Moreover, development of remaining infrastructure in the sector is also in pipeline.

Similarly, authority in addition to...